Novarly ParcelRenewable sites

Renewable sitesSleaford Renewable Energy Plant

Sleaford Renewable Energy Plant

Sleaford Renewable Energy Plant is an operational 40 MW biomass plant in North Kesteven, generating since 28 November 2014. Planning permission was granted on 4 November 2008, 2 months after submission. Operator of record: Glenmont Partners.

40 MW
Capacity
as recorded in REPD
Operational
Status
since 28 November 2014
Biomass (dedicated)
Technology
Glenmont Partners
North Kesteven
Authority
England

Planning and build timeline

Application submitted20 August 2008
Permission granted4 November 2008
2 months after submission
Operational28 November 2014
73 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in North Kesteven: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Sleaford Renewable Energy Plant’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
252.8 km
Solar Photovoltaics · Operational
83.4 km
Solar Photovoltaics · Operational
153.5 km
Solar Photovoltaics · Under Construction
204 km
Solar Photovoltaics · Operational
32.59.5 km
Wind Onshore · Operational
26.713 km
Solar Photovoltaics · Under Construction
7514.4 km
Battery · Under Construction
5014.4 km

How big is Sleaford Renewable Energy Plant?

Sleaford Renewable Energy Plant has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Sleaford Renewable Energy Plant?

REPD records the operator as Glenmont Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Sleaford Renewable Energy Plant approved and built?

The application was submitted on 20 August 2008. Permission was granted on 4 November 2008, 2 months later. The site became operational on 28 November 2014, 73 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 206.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode