Ermine Street Farm solar park

Ermine Street Farm solar park is an operational 32.5 MW solar farm in North Kesteven, generating since 29 July 2014. Planning permission was granted on 6 December 2013, 4 months after submission. Operator of record: Octopus Investments.

32.5 MW
Capacity
as recorded in REPD
Operational
Status
since 29 July 2014
Solar Photovoltaics
Technology
Octopus Investments
North Kesteven
Authority
England

Planning and build timeline

Application submitted20 August 2013
Permission granted6 December 2013
4 months after submission
Operational29 July 2014
8 months after consent

Screening a site of your own?

RedlineUK · £39

North Kesteven approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ermine Street Farm solar park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Kesteven’s record on solar

North Kesteven has decided 26 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in North Kesteven

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
88.3 km
Solar Photovoltaics · Under Construction
209 km
Biomass (dedicated) · Operational
409.5 km
Biomass (dedicated) · Under Construction
1.610.9 km
Solar Photovoltaics · Under Construction
2511.3 km
Biomass (dedicated) · Under Construction
1.611.8 km
Solar Photovoltaics · Operational
1512.1 km
Solar Photovoltaics · Operational
4.912.5 km

How big is Ermine Street Farm solar park?

Ermine Street Farm solar park has a recorded installed capacity of 32.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ermine Street Farm solar park?

REPD records the operator as Octopus Investments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ermine Street Farm solar park approved and built?

The application was submitted on 20 August 2013. Permission was granted on 6 December 2013, 4 months later. The site became operational on 29 July 2014, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1528.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode