Novarly ParcelRenewable sites

Renewable sitesDeepdale Farm

Deepdale Farm

Deepdale Farm is an operational 8 MW solar farm in North Kesteven, generating since 30 June 2016. Planning permission was granted on 10 November 2014, 4 months after submission. Operator of record: Deepdale Farm Solar Ltd.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 30 June 2016
Solar Photovoltaics
Technology
Deepdale Farm Solar Ltd
North Kesteven
Authority
England

Planning and build timeline

Application submitted16 July 2014
Permission granted10 November 2014
4 months after submission
Operational30 June 2016
20 months after consent

Screening a site of your own?

RedlineUK · £39

North Kesteven approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Deepdale Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Kesteven’s record on solar

North Kesteven has decided 26 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in North Kesteven

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
403.4 km
Solar Photovoltaics · Under Construction
256.2 km
Solar Photovoltaics · Under Construction
206.7 km
Solar Photovoltaics · Operational
156.8 km
Solar Photovoltaics · Operational
32.58.3 km
Anaerobic Digestion · Operational
6.512.8 km

How big is Deepdale Farm?

Deepdale Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Deepdale Farm?

REPD records the operator as Deepdale Farm Solar Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Deepdale Farm approved and built?

The application was submitted on 16 July 2014. Permission was granted on 10 November 2014, 4 months later. The site became operational on 30 June 2016, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2204.

Novarly Parcel · official public data, read properly · parcel.novarly.com