Novarly ParcelRenewable sites

Renewable sitesBicker Fen

Bicker Fen

Bicker Fen is operational in Boston with a recorded capacity of 26.7 MW, and has been generating since 2008-07-28.

26.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2008-07-28
Wind Onshore
Technology
Wind Prospect
Boston
Authority
England

Planning and build timeline

Application submitted2003-03-10
Permission granted2004-10-15
19 months after submission
Operational2008-07-28
45 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Cowbridge Road, Bicker Fen - Solar Array
Solar Photovoltaics · Under Construction
751.8 km
Cowbridge Road, Bicker Fen - Battery Storage
Battery · Under Construction
501.8 km
Nowhere Farm
Solar Photovoltaics · Operational
8.17.7 km
Kirton Solar PV Farm
Solar Photovoltaics · Operational
3.28.2 km
Grange Farm (Burton Pedwardine)
Solar Photovoltaics · Operational
1510 km
Fen Road
Solar Photovoltaics · Operational
1.410.3 km
White Cross Lane
Solar Photovoltaics · Under Construction
2510.8 km
Sleaford Renewable Energy Plant
Biomass (dedicated) · Operational
4013 km

How big is Bicker Fen?

Bicker Fen has a recorded installed capacity of 26.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bicker Fen?

REPD records the operator as Wind Prospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bicker Fen approved and built?

The application was submitted on 2003-03-10. Permission was granted on 2004-10-15, 19 months later. The site became operational on 2008-07-28, 45 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3128.