Renewable sites › Bicker Fen
Bicker Fen
Bicker Fen is an operational 26.7 MW onshore wind farm in Boston, generating since 28 July 2008. Planning permission was granted on 15 October 2004, 19 months after submission. Operator of record: Wind Prospect.
Planning and build timeline
| Application submitted | 10 March 2003 |
| Permission granted | 15 October 2004 19 months after submission |
| Operational | 28 July 2008 45 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Boston: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Bicker Fen’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | 50 | 1.8 km |
Solar Photovoltaics · Under Construction | 75 | 1.8 km |
Solar Photovoltaics · Operational | 8.1 | 7.7 km |
Solar Photovoltaics · Operational | 3.2 | 8.2 km |
Solar Photovoltaics · Operational | 15 | 10 km |
Solar Photovoltaics · Operational | 1.4 | 10.3 km |
Solar Photovoltaics · Under Construction | 25 | 10.8 km |
Biomass (dedicated) · Operational | 40 | 13 km |
How big is Bicker Fen?
Bicker Fen has a recorded installed capacity of 26.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bicker Fen?
REPD records the operator as Wind Prospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bicker Fen approved and built?
The application was submitted on 10 March 2003. Permission was granted on 15 October 2004, 19 months later. The site became operational on 28 July 2008, 45 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3128.