Singleton Birch (Farm AD)
Singleton Birch (Farm AD) is an operational 1.5 MW anaerobic digestion plant in North Lincolnshire, generating since 21 March 2014. Planning permission was granted on 11 March 2013, 3 months after submission. Operator of record: Singleton Birch.
Planning and build timeline
| Application submitted | 12 December 2012 |
| Permission granted | 11 March 2013 3 months after submission |
| Operational | 21 March 2014 12 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in North Lincolnshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Singleton Birch (Farm AD)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Advanced Conversion Technologies · Operational | 5.8 | 0.7 km |
Anaerobic Digestion · Operational | 1.5 | 8.7 km |
Solar Photovoltaics · Operational | 0.24 | 10 km |
Biomass (dedicated) · Operational | 40 | 11.5 km |
Landfill Gas · Operational | 1 | 11.6 km |
Landfill Gas · Operational | 2 | 11.6 km |
Battery · Under Construction | 80 | 11.8 km |
Solar Photovoltaics · Under Construction | 49.9 | 12.6 km |
How big is Singleton Birch (Farm AD)?
Singleton Birch (Farm AD) has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Singleton Birch (Farm AD)?
REPD records the operator as Singleton Birch. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Singleton Birch (Farm AD) approved and built?
The application was submitted on 12 December 2012. Permission was granted on 11 March 2013, 3 months later. The site became operational on 21 March 2014, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 260.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode