Renewable sites › Singleton Birch (Farm AD)
Singleton Birch (Farm AD)
Singleton Birch (Farm AD) is operational in North Lincolnshire with a recorded capacity of 1.5 MW, and has been generating since 2014-03-21.
Planning and build timeline
| Application submitted | 2012-12-12 |
| Permission granted | 2013-03-11 3 months after submission |
| Operational | 2014-03-21 12 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Melton Ross Advanced Conversion Technologies · Operational | 5.8 | 0.7 km |
Bonby Lane Anaerobic Digestion · Operational | 1.5 | 8.7 km |
Atherton Way - Solar Panels Solar Photovoltaics · Operational | 0.24 | 10 km |
Brigg Renewable Energy Plant Biomass (dedicated) · Operational | 40 | 11.5 km |
Immingham Landfill Gas · Operational | 2 | 11.6 km |
Immingham Landfill Scheme Landfill Gas · Operational | 1 | 11.6 km |
Trondheim Way Battery energy storage Battery · Under Construction | 80 | 11.8 km |
Grimsby Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 12.6 km |
How big is Singleton Birch (Farm AD)?
Singleton Birch (Farm AD) has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Singleton Birch (Farm AD)?
REPD records the operator as Singleton Birch. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Singleton Birch (Farm AD) approved and built?
The application was submitted on 2012-12-12. Permission was granted on 2013-03-11, 3 months later. The site became operational on 2014-03-21, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 260.
Novarly Parcel · official public data, read properly · parcel.novarly.com