Novarly ParcelRenewable planning

Renewable planning Onshore windSomerset

Onshore wind planning in Somerset

Somerset has decided 9 onshore wind schemes and approved 22% of them, taking a median of 11.7 months to decide. Consented capacity: 2 MW. 2 applications still awaiting a decision.

22%
Approved
2 granted · 7 refused
11.7 mo
Median decision
UK 11.5 mo
2 MW
Consented
82 MW refused
4
Appeals
1 allowed on appeal

How Somerset compares

Against the 75 UK authorities with 5+ onshore wind decisions, Somerset sits in the 4th percentile for approval rate (46 points below the England average) and the 62nd percentile for speed.

Decisions by year

35Refused — 1 (2012)112Refused — 1 (2013)113Refused — 1 (2014)114Refused — 1 (2015)115Approved — 1 (2025)125
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (13)

SchemeMWStatusDecided
Warren Farm, Masbury - Wind Turbine
Constantine Group Limited · 2024/1807/FUL · 10 mo to decide
0.33Awaiting Construction2025-11-28
Landmark Farm, Burts Hill To Nunney Catch Roundabout - Wind Turbine
Distgen Limited · 2024/1931/FUL
2Application Submitted2024-11-04
Withy End
EDF Energy Renewables · 54/13/00023 · 16.4 mo to decide
10Application Refused2015-05-07
West Hinkley Wind Farm (withdrawn)
EDF / Your Energy · 3/32/06/032
18Application Withdrawn2014-09-25
Torr Works
Aggregate Industries UK · 2013/1244 · 9.7 mo to decide
3.6Appeal Refused2014-04-16
Pilrow
Broadview Energy Limited · 24/12/00018 · 9.3 mo to decide
12Appeal Refused2013-04-08
Black Ditch
Ecotricity · 52/10/00018 · 16.8 mo to decide
9.2Application Refused2012-04-24
Withy Farm
EDF Energy · 54/11/00004 · 13.5 mo to decide
10Revised2012-04-24
Cricket St Thomas
National Wind Power · 02/01865/FUL
3.9Application Withdrawn2011-06-29
Inner Farm
Ecotricity · 12/06/00007 · 4.6 mo to decide
10Application Refused2006-08-08
Shooters Bottom Wind Park
Ecotricity · 116407-000 · 32.1 mo to decide
2Operational2006-05-18
West Hinkley Wind Farm
Your Energy · 3/32/04/022 · 14.8 mo to decide
33Application Refused2005-10-26
Symphony Farm
Ecotricity · 03480FUL · 5.3 mo to decide
3.9Application Refused2004-03-09

Does Somerset approve onshore wind schemes?

Yes — of the 9 onshore wind schemes Somerset has decided, 22% were approved (2 granted, 7 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Somerset?

The median time from application to decision is 11.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Somerset consented?

2 MW has been consented across 2 approved schemes, with 82 MW refused. A further 2 applications awaits a decision.

Other technologies in Somerset

Solar in SomersetBattery storage in Somerset

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.