Novarly ParcelRenewable sites

Renewable sitesNew Row Farm

New Row Farm

New Row Farm is operational in Somerset with a recorded capacity of 3.9 MW, and has been generating since 2014-03-31.

3.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-31
Solar Photovoltaics
Technology
Lightsource Renewable Energy
Somerset
Authority
England

Planning and build timeline

Application submitted2013-08-05
Permission granted2013-11-11
3 months after submission
Operational2014-03-31
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Lodge Farm Solar Farm
Solar Photovoltaics · Under Construction
51.6 km
Framptons Limited Energy Centre
Biomass (dedicated) · Under Construction
3.92 km
Crapnell Farm Solar Farm
Solar Photovoltaics · Operational
5.43.6 km
Burges Lane, Stoke St Michael - Solar Array Panels
Solar Photovoltaics · Under Construction
1.783.8 km
Pitts Farm
Solar Photovoltaics · Operational
2.64.2 km
Pylle Southern solar park (Lower Easton Farm)
Solar Photovoltaics · Operational
56.5 km
Shooters Bottom Wind Park
Wind Onshore · Operational
26.8 km
Land at Soho Farm
Solar Photovoltaics · Operational
1.57 km

How big is New Row Farm?

New Row Farm has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates New Row Farm?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was New Row Farm approved and built?

The application was submitted on 2013-08-05. Permission was granted on 2013-11-11, 3 months later. The site became operational on 2014-03-31, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2133.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council