Renewable sites › Pitts Farm
Pitts Farm
Pitts Farm is operational in Somerset with a recorded capacity of 2.6 MW, and has been generating since 2014-03-28.
Planning and build timeline
| Application submitted | 2013-04-10 |
| Permission granted | 2013-06-07 2 months after submission |
| Operational | 2014-03-28 10 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — Brue Catchment
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Somerset’s record on solar
Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crapnell Farm Solar Farm Solar Photovoltaics · Operational | 5.4 | 0.7 km |
New Row Farm Solar Photovoltaics · Operational | 3.9 | 4.2 km |
Priddy Road Farm Biomass Boiler (Retrospective) Biomass (dedicated) · Operational | — | 4.3 km |
Shooters Bottom Wind Park Wind Onshore · Operational | 2 | 4.5 km |
Framptons Limited Energy Centre Biomass (dedicated) · Under Construction | 3.9 | 4.7 km |
Shooters Bottom Solar Park Solar Photovoltaics · Operational | 7 | 5 km |
Lodge Farm Solar Farm Solar Photovoltaics · Under Construction | 5 | 5.7 km |
Burges Lane, Stoke St Michael - Solar Array Panels Solar Photovoltaics · Under Construction | 1.78 | 7.6 km |
How big is Pitts Farm?
Pitts Farm has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pitts Farm?
REPD records the operator as Lightsource BP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pitts Farm approved and built?
The application was submitted on 2013-04-10. Permission was granted on 2013-06-07, 2 months later. The site became operational on 2014-03-28, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2127.