Novarly ParcelRenewable sites

Renewable sitesSheepbridge Court Farm

Sheepbridge Court Farm

Sheepbridge Court Farm is an operational 5 MW solar farm in Wokingham, generating since 20 December 2015. Planning permission was granted on 12 December 2014, 4 months after submission. Operator of record: Foresight.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 20 December 2015
Solar Photovoltaics
Technology
Foresight
Wokingham
Authority
England

Planning and build timeline

Application submitted5 August 2014
Permission granted12 December 2014
4 months after submission
Operational20 December 2015
12 months after consent

Screening a site of your own?

RedlineUK · £39

Wokingham approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Sheepbridge Court Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wokingham’s record on solar

Wokingham has decided 12 solar farms and approved 100%, taking a median of 1.7 months. See every solar farm decision in Wokingham

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
142.8 km
Wind Onshore · Operational
23.7 km
Solar Photovoltaics · Operational
1.74.4 km
Solar Photovoltaics · Operational
15.84.8 km
Solar Photovoltaics · Under Construction
17.876.9 km
Battery · Operational
1009.8 km
Solar Photovoltaics · Under Construction
49.910 km
Battery · Under Construction
10 km

How big is Sheepbridge Court Farm?

Sheepbridge Court Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Sheepbridge Court Farm?

REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Sheepbridge Court Farm approved and built?

The application was submitted on 5 August 2014. Permission was granted on 12 December 2014, 4 months later. The site became operational on 20 December 2015, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2244.