Renewable sitesPierces Farm

Pierces Farm

Pierces Farm is an operational 1.7 MW solar farm in West Berkshire, generating since 15 March 2015. Planning permission was granted on 19 March 2014, 3 months after submission. Operator of record: NextEnergy Capital.

1.7 MW
Capacity
as recorded in REPD
Operational
Status
since 15 March 2015
Solar Photovoltaics
Technology
NextEnergy Capital
West Berkshire
Authority
England

Planning and build timeline

Application submitted23 December 2013
Permission granted19 March 2014
3 months after submission
Operational15 March 2015
12 months after consent

Screening a site of your own?

RedlineUK · £39

West Berkshire approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pierces Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Berkshire’s record on solar

West Berkshire has decided 22 solar farms and approved 95%, taking a median of 2.8 months. See every solar farm decision in West Berkshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
15.82 km
Wind Onshore · Operational
23.3 km
Solar Photovoltaics · Operational
54.4 km
Solar Photovoltaics · Under Construction
147.2 km
Battery · Operational
1008.3 km
Solar Photovoltaics · Under Construction
17.879.1 km
Solar Photovoltaics · Operational
4.210.2 km
Battery · Operational
110.3 km

How big is Pierces Farm?

Pierces Farm has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pierces Farm?

REPD records the operator as NextEnergy Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pierces Farm approved and built?

The application was submitted on 23 December 2013. Permission was granted on 19 March 2014, 3 months later. The site became operational on 15 March 2015, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1306.