Pierces Farm is operational in West Berkshire with a recorded capacity of 1.7 MW, and has been generating since 2015-03-15.

1.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-15
Solar Photovoltaics
Technology
NextEnergy Capital
West Berkshire
Authority
England

Planning and build timeline

Application submitted2013-12-23
Permission granted2014-03-19
3 months after submission
Operational2015-03-15
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Berkshire’s record on solar

West Berkshire has decided 22 solar farms and approved 95%, taking a median of 2.8 months. See every solar farm decision in West Berkshire

Other built sites within 15 km

SiteMWDistance
Pingewood Road South
Solar Photovoltaics · Operational
15.82 km
Green Park
Wind Onshore · Operational
23.3 km
Sheepbridge Court Farm
Solar Photovoltaics · Operational
54.4 km
Aborfield Solar Park
Solar Photovoltaics · Under Construction
147.2 km
Minchens Lane Battery Storage Facility
Battery · Operational
1008.3 km
Kiln Fields Solar Farm
Solar Photovoltaics · Under Construction
17.879.1 km
Berry Court Farm
Solar Photovoltaics · Operational
4.210.2 km
Berry Court Solar Farm - energy storage
Battery · Operational
110.3 km

How big is Pierces Farm?

Pierces Farm has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pierces Farm?

REPD records the operator as NextEnergy Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pierces Farm approved and built?

The application was submitted on 2013-12-23. Permission was granted on 2014-03-19, 3 months later. The site became operational on 2015-03-15, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1306.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council