Solar planning in Wokingham

Wokingham has decided 12 solar farms and approved 100% of them, taking a median of 1.7 months to decide. Consented capacity: 82 MW.

100%
Approved
12 granted · 0 refused
1.7 mo
Median decision
UK 2.3 mo
82 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Wokingham compares

Against the 298 UK authorities with 5+ solar decisions, Wokingham sits in the 77th percentile for approval rate (7 points above the England average) and the 87th percentile for speed.

Decisions by year

35Approved — 1 (2014)114Approved — 3 (2021)321Approved — 3 (2022)322Approved — 3 (2023)323Approved — 2 (2025)225
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (12)

SchemeMWStatusDecided
Mereoak Park And Ride, Mereoak Lane - Solar Canopies
Wokingham Borough Council · 252226 · 1.8 mo to decide
Awaiting Construction2025-11-10
Spencers Wood Solar Farm, Basingstoke Road - Solar Array
Greentech · 232653 · 16.1 mo to decide
28Awaiting Construction2025-03-26
Henry Street Garden Centre, Swallowfield Road, - Solar Panels
Henry Street Garden Centre · 232714 · 0.8 mo to decide
0.38Awaiting Construction2023-11-29
Suttons Park Avenue, Suttons Business Park - Solar PV
Brakes Group · 231133 · 1.5 mo to decide
1.3Awaiting Construction2023-08-11
David Lloyd Leisure, Thames Valley Park Drive - Solar Panels
David Lloyd Leisure Limited · 231020 · 1.6 mo to decide
Awaiting Construction2023-06-20
Eskdale Road, Winnersh - Solar Panels
Winnersh Midco SARL · 222536 · 0.8 mo to decide
0.19Awaiting Construction2022-09-15
Thames Valley Park Drive, Earley - Photovoltaic Solar panels
Oracle Hospitality · 221111 · 1.2 mo to decide
0.16Awaiting Construction2022-05-13
Barkham Farms - Solar Farm
Wokingham Borough Council · 211081 · 9.9 mo to decide
33Awaiting Construction2022-01-21
Woodley Library Solar Planels
Wokingham Borough Council · 211597 · 1 mo to decide
Awaiting Construction2021-06-17
Rectory Road - Roof Mounted Solar panels
Wokingham Borough Council · 210825 · 3 mo to decide
Awaiting Construction2021-04-21
Aborfield Solar Park
Wessex Solar Energy · 200711 · 11.6 mo to decide
14Under Construction2021-03-12
Sheepbridge Court Farm
Foresight · F/2014/1495 · 4.2 mo to decide
5Operational2014-12-12

Does Wokingham approve solar farms?

Yes — of the 12 solar farms Wokingham has decided, 100% were approved (12 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Wokingham?

The median time from application to decision is 1.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Wokingham consented?

82 MW has been consented across 12 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Wokingham

Battery storage in WokinghamOnshore wind in Wokingham

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report