Green Park
Green Park is operational in Wokingham with a recorded capacity of 2 MW, and has been generating since 2005-10-01.
Planning and build timeline
| Application submitted | 2004-03-17 |
| Permission granted | 2004-07-28 4 months after submission |
| Operational | 2005-10-01 14 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pingewood Road South Solar Photovoltaics · Operational | 15.8 | 2 km |
Pierces Farm Solar Photovoltaics · Operational | 1.7 | 3.3 km |
Sheepbridge Court Farm Solar Photovoltaics · Operational | 5 | 3.7 km |
Aborfield Solar Park Solar Photovoltaics · Under Construction | 14 | 5.8 km |
Kiln Fields Solar Farm Solar Photovoltaics · Under Construction | 17.87 | 10.3 km |
Minchens Lane Battery Storage Facility Battery · Operational | 100 | 11.3 km |
Berry Court Farm Solar Photovoltaics · Operational | 4.2 | 13.4 km |
Bunkers Hill Farm - Solar farm & Battery stations Solar Photovoltaics · Under Construction | 49.9 | 13.4 km |
How big is Green Park?
Green Park has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Green Park?
REPD records the operator as Ecotricity / Prudential. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Green Park approved and built?
The application was submitted on 2004-03-17. Permission was granted on 2004-07-28, 4 months later. The site became operational on 2005-10-01, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3210.