Says Court Farm solar park is operational in South Gloucestershire with a recorded capacity of 19.8 MW, and has been generating since 2014-03-31.

19.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-31
Solar Photovoltaics
Technology
AEE Renewables
South Gloucestershire
Authority
England

Planning and build timeline

Application submitted2013-04-09
Permission granted2013-10-01
6 months after submission
Operational2014-03-31
6 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Gloucestershire’s record on solar

South Gloucestershire has decided 54 solar farms and approved 96%, taking a median of 1.8 months. See every solar farm decision in South Gloucestershire

Other built sites within 15 km

SiteMWDistance
Perrinpit Farm
Solar Photovoltaics · Under Construction
49.93.5 km
Grange Farm (Avon)
Solar Photovoltaics · Operational
215.1 km
Larks Green Solar Farm
Battery · Operational
49.55.3 km
Larks Green Solar Farm
Solar Photovoltaics · Operational
705.3 km
Amcor Flexibles
Solar Photovoltaics · Operational
1.75.5 km
Alveston Wind Park
Wind Onshore · Operational
6.95.5 km
Hammond Court Farm
Solar Photovoltaics · Operational
155.7 km
Ring O Bells Farm
Solar Photovoltaics · Operational
56.2 km

How big is Says Court Farm solar park?

Says Court Farm solar park has a recorded installed capacity of 19.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Says Court Farm solar park?

REPD records the operator as AEE Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Says Court Farm solar park approved and built?

The application was submitted on 2013-04-09. Permission was granted on 2013-10-01, 6 months later. The site became operational on 2014-03-31, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1663.