Renewable sites › Alveston Wind Park
Alveston Wind Park
Alveston Wind Park is operational in South Gloucestershire with a recorded capacity of 6.9 MW, and has been generating since 2017-12-07.
Planning and build timeline
| Application submitted | 2008-06-02 |
| Permission granted | 2008-11-13 5 months after submission |
| Operational | 2017-12-07 109 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — South Gloucestershire
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Larks Green Solar Farm Solar Photovoltaics · Operational | 70 | 1.7 km |
Larks Green Solar Farm Battery · Operational | 49.5 | 1.7 km |
Perrinpit Farm Solar Photovoltaics · Under Construction | 49.9 | 3 km |
Tower Hill Farm Solar Photovoltaics · Operational | 8.1 | 3.4 km |
Grange Farm (Avon) Solar Photovoltaics · Operational | 21 | 4 km |
Parklands Solar Photovoltaics · Operational | 4.6 | 4 km |
Hammond Court Farm Solar Photovoltaics · Operational | 15 | 4.3 km |
Says Court Farm solar park Solar Photovoltaics · Operational | 19.8 | 5.5 km |
How big is Alveston Wind Park?
Alveston Wind Park has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Alveston Wind Park?
REPD records the operator as Ecotricity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Alveston Wind Park approved and built?
The application was submitted on 2008-06-02. Permission was granted on 2008-11-13, 5 months later. The site became operational on 2017-12-07, 109 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4335.