Perrinpit Farm
Perrinpit Farm is a 49.9 MW solar farm under construction in South Gloucestershire. Planning permission was granted on 21 September 2022, 18 months after submission. Operator of record: Grune Energien.
Planning and build timeline
| Application submitted | 12 March 2021 |
| Permission granted | 21 September 2022 18 months after submission |
| Operational | not recorded |
Screening a site of your own?
South Gloucestershire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Perrinpit Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — South Gloucestershire
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Gloucestershire’s record on solar
South Gloucestershire has decided 54 solar farms and approved 96%, taking a median of 1.8 months. See every solar farm decision in South Gloucestershire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 21 | 1.9 km |
Solar Photovoltaics · Operational | 15 | 2.5 km |
Wind Onshore · Operational | 6.9 | 3 km |
Solar Photovoltaics · Operational | 1.7 | 3.3 km |
Solar Photovoltaics · Operational | 19.8 | 3.5 km |
Solar Photovoltaics · Operational | 70 | 3.9 km |
Battery · Operational | 49.5 | 3.9 km |
Solar Photovoltaics · Operational | 4.6 | 4.1 km |
How big is Perrinpit Farm?
Perrinpit Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Perrinpit Farm?
REPD records the operator as Grune Energien. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Perrinpit Farm approved and built?
The application was submitted on 12 March 2021. Permission was granted on 21 September 2022, 18 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7944.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode