Novarly ParcelRenewable sites

Renewable sitesSancton Hill

Sancton Hill

Sancton Hill is operational in East Riding of Yorkshire with a recorded capacity of 10 MW, and has been generating since 2012-06-12.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-06-12
Wind Onshore
Technology
REG Windpower (previously Cornwall Light and Power)
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted2010-05-17
Permission granted2011-02-10
9 months after submission
Operational2012-06-12
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on onshore wind

East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Sober Hill Wind Farm
Wind Onshore · Operational
151.4 km
Gallymoor Landfill
Landfill Gas · Operational
2.97.7 km
Brocklesby - Crosslands Lane
Anaerobic Digestion · Operational
3.58.3 km
Normandy Barracks
Solar Photovoltaics · Under Construction
2.311.7 km
R G Walter & Sons, Golden Acre Site - Biomass Boilers
Biomass (dedicated) · Operational
0.913.4 km
Cottingham - Solar Farm
Solar Photovoltaics · Operational
513.4 km
Creyke Beck
Battery · Operational
49.913.5 km
Pillswood Phase 2
Battery · Operational
49.513.6 km

How big is Sancton Hill?

Sancton Hill has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Sancton Hill?

REPD records the operator as REG Windpower (previously Cornwall Light and Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Sancton Hill approved and built?

The application was submitted on 2010-05-17. Permission was granted on 2011-02-10, 9 months later. The site became operational on 2012-06-12, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3735.