Renewable sites › Gallymoor Landfill
Gallymoor Landfill
Gallymoor Landfill is operational in East Riding of Yorkshire with a recorded capacity of 2.9 MW, and has been generating since 2004-04-01.
Planning and build timeline
| Application submitted | 1994-11-02 |
| Permission granted | 1995-01-20 3 months after submission |
| Operational | 2004-04-01 110 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Spaldington Airfield Wind Onshore · Operational | 12.5 | 7.4 km |
Sancton Hill Wind Onshore · Operational | 10 | 7.7 km |
Brocklesby - Crosslands Lane Anaerobic Digestion · Operational | 3.5 | 8.6 km |
Sober Hill Wind Farm Wind Onshore · Operational | 15 | 8.6 km |
Soay Solar Farm and Greener Grid Park Solar Photovoltaics · Under Construction | 49.99 | 8.6 km |
Soay Solar Farm and Greener Grid Park Battery · Under Construction | 200 | 8.6 km |
R G Walter & Sons, Golden Acre Site - Biomass Boilers Biomass (dedicated) · Operational | 0.9 | 9.4 km |
Sixpenny Wood Windfarm Wind Onshore · Operational | 33 | 13.3 km |
How big is Gallymoor Landfill?
Gallymoor Landfill has a recorded installed capacity of 2.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gallymoor Landfill?
REPD records the operator as FCC Environment. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gallymoor Landfill approved and built?
The application was submitted on 1994-11-02. Permission was granted on 1995-01-20, 3 months later. The site became operational on 2004-04-01, 110 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 770.
Novarly Parcel · official public data, read properly · parcel.novarly.com