Renewable sites › Roosecote
Roosecote
Roosecote is an operational 49 MW battery storage site in Westmorland and Furness, generating since 30 November 2018. REPD does not record the planning grant date. Operator of record: Centrica.
Planning and build timeline
| Application submitted | not recorded |
| Permission granted | not recorded |
| Operational | 30 November 2018 |
Screening a site of your own?
Westmorland and Furness approves 71% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Roosecote’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Westmorland and Furness’s record on battery storage
Westmorland and Furness has decided 7 battery storage schemes and approved 71%, taking a median of 8.8 months. See every battery storage scheme decision in Westmorland and Furness →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 5 km |
Landfill Gas · Operational | 2.2 | 6.2 km |
Solar Photovoltaics · Operational | 6.5 | 7.8 km |
Wind Onshore · Operational | 4.6 | 8.8 km |
Wind Onshore · Operational | 2.5 | 11.4 km |
Wind Onshore · Operational | 11.5 | 11.9 km |
Wind Onshore · Operational | 2.4 | 14.1 km |
Wind Onshore · Operational | 1.2 | 14.1 km |
How big is Roosecote?
Roosecote has a recorded installed capacity of 49 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Roosecote?
REPD records the operator as Centrica. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Roosecote approved and built?
REPD does not record a submission date. REPD does not record a grant date. The site became operational on 30 November 2018.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6912.
Novarly Parcel · official public data, read properly · parcel.novarly.com