Renewable sites › Haverigg Repowering (Haverigg II)
Haverigg Repowering (Haverigg II)
Haverigg Repowering (Haverigg II) is an operational 1.2 MW onshore wind farm in Cumberland, generating since 1 May 2004. Planning permission was granted on 15 August 2002, 4 months after submission. Operator of record: Windprospect.
Planning and build timeline
| Application submitted | 29 April 2002 |
| Permission granted | 15 August 2002 4 months after submission |
| Operational | 1 May 2004 21 months after consent |
Screening a site of your own?
Cumberland approves 66% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Haverigg Repowering (Haverigg II)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cumberland’s record on onshore wind
Cumberland has decided 38 onshore wind schemes and approved 66%, taking a median of 10.3 months. See every onshore wind scheme decision in Cumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 2.4 | 0 km |
Solar Photovoltaics · Operational | 6.5 | 8.2 km |
Solar Photovoltaics · Operational | 5 | 9.1 km |
Landfill Gas · Operational | 2.2 | 9.3 km |
Wind Onshore · Operational | 4.6 | 9.6 km |
Wind Onshore · Operational | 11.5 | 11.6 km |
Wind Onshore · Operational | 2.5 | 11.6 km |
Wind Onshore · Operational | 4.8 | 13.7 km |
How big is Haverigg Repowering (Haverigg II)?
Haverigg Repowering (Haverigg II) has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Haverigg Repowering (Haverigg II)?
REPD records the operator as Windprospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Haverigg Repowering (Haverigg II) approved and built?
The application was submitted on 29 April 2002. Permission was granted on 15 August 2002, 4 months later. The site became operational on 1 May 2004, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3614.