Novarly ParcelRenewable sites

Renewable sitesFurness Wind Farm/High Winds (Harlock Repowering)

Furness Wind Farm/High Winds (Harlock Repowering)

Furness Wind Farm/High Winds (Harlock Repowering) is an operational 11.5 MW onshore wind farm in Westmorland and Furness, generating since 17 November 2016. Planning permission was granted on 24 July 2014, 35 months after submission. Operator of record: Baywind Co-op & Energy4All & Belltown Power.

11.5 MW
Capacity
as recorded in REPD
Operational
Status
since 17 November 2016
Wind Onshore
Technology
Baywind Co-op & Energy4All & Belltown Power
Westmorland and Furness
Authority
England

Planning and build timeline

Application submitted6 September 2011
Permission granted24 July 2014
35 months after submission
Operational17 November 2016
28 months after consent

Screening a site of your own?

RedlineUK · £39

Westmorland and Furness approves 35% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Furness Wind Farm/High Winds (Harlock Repowering)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Westmorland and Furness’s record on onshore wind

Westmorland and Furness has decided 17 onshore wind schemes and approved 35%, taking a median of 16.8 months. See every onshore wind scheme decision in Westmorland and Furness

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.50.5 km
Wind Onshore · Operational
4.63.6 km
Wind Onshore · Operational
4.85.4 km
Solar Photovoltaics · Operational
6.55.6 km
Landfill Gas · Operational
2.26.6 km
Solar Photovoltaics · Operational
59.9 km
Wind Onshore · Operational
2.411.6 km
Wind Onshore · Operational
1.211.6 km

How big is Furness Wind Farm/High Winds (Harlock Repowering)?

Furness Wind Farm/High Winds (Harlock Repowering) has a recorded installed capacity of 11.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Furness Wind Farm/High Winds (Harlock Repowering)?

REPD records the operator as Baywind Co-op & Energy4All & Belltown Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Furness Wind Farm/High Winds (Harlock Repowering) approved and built?

The application was submitted on 6 September 2011. Permission was granted on 24 July 2014, 35 months later. The site became operational on 17 November 2016, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4177.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode