Harlock Hill Wind Farm
Harlock Hill Wind Farm is an operational 2.5 MW onshore wind farm in Westmorland and Furness, generating since 1 January 1997. Planning permission was granted on 3 May 1996, 15 months after submission. Operator of record: The Wind Company.
Planning and build timeline
| Application submitted | 3 February 1995 |
| Permission granted | 3 May 1996 15 months after submission |
| Operational | 1 January 1997 8 months after consent |
Screening a site of your own?
Westmorland and Furness approves 35% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Harlock Hill Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Westmorland and Furness’s record on onshore wind
Westmorland and Furness has decided 17 onshore wind schemes and approved 35%, taking a median of 16.8 months. See every onshore wind scheme decision in Westmorland and Furness →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 11.5 | 0.5 km |
Wind Onshore · Operational | 4.6 | 3.3 km |
Solar Photovoltaics · Operational | 6.5 | 5.3 km |
Wind Onshore · Operational | 4.8 | 5.9 km |
Landfill Gas · Operational | 2.2 | 6.2 km |
Solar Photovoltaics · Operational | 5 | 9.5 km |
Battery · Operational | 49 | 11.4 km |
Wind Onshore · Operational | 2.4 | 11.6 km |
How big is Harlock Hill Wind Farm?
Harlock Hill Wind Farm has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Harlock Hill Wind Farm?
REPD records the operator as The Wind Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Harlock Hill Wind Farm approved and built?
The application was submitted on 3 February 1995. Permission was granted on 3 May 1996, 15 months later. The site became operational on 1 January 1997, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2617.
Novarly Parcel · official public data, read properly · parcel.novarly.com