Planning and build timeline
| Application submitted | 1995-02-03 |
| Permission granted | 1996-05-03 15 months after submission |
| Operational | 1997-01-01 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Westmorland and Furness’s record on onshore wind
Westmorland and Furness has decided 17 onshore wind schemes and approved 35%, taking a median of 16.8 months. See every onshore wind scheme decision in Westmorland and Furness →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Furness Wind Farm/High Winds (Harlock Repowering) Wind Onshore · Operational | 11.5 | 0.5 km |
Askam Wind Onshore · Operational | 4.6 | 3.3 km |
Roanhead Farm Solar Photovoltaics · Operational | 6.5 | 5.3 km |
Kirkby Moor Wind Onshore · Operational | 4.8 | 5.9 km |
Bennett Bank Landfill Site (lfg) Landfill Gas · Operational | 2.2 | 6.2 km |
Sowerby Lodge Farm Solar Photovoltaics · Operational | 5 | 9.5 km |
Roosecote Battery · Operational | 49 | 11.4 km |
Haverigg Extension Wind Farm Wind Onshore · Operational | 2.4 | 11.6 km |
How big is Harlock Hill Wind Farm?
Harlock Hill Wind Farm has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Harlock Hill Wind Farm?
REPD records the operator as The Wind Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Harlock Hill Wind Farm approved and built?
The application was submitted on 1995-02-03. Permission was granted on 1996-05-03, 15 months later. The site became operational on 1997-01-01, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2617.
Novarly Parcel · official public data, read properly · parcel.novarly.com