Rookwood Way - Solar Farm is an operational 2.04 MW solar farm in West Suffolk, generating since 1 May 2024. Planning permission was granted on 29 June 2023, 5 months after submission. Operator of record: Sanofi UK.

2.04 MW
Capacity
as recorded in REPD
Operational
Status
since 1 May 2024
Solar Photovoltaics
Technology
Sanofi UK
West Suffolk
Authority
England

Planning and build timeline

Application submitted3 February 2023
Permission granted29 June 2023
5 months after submission
Operational1 May 2024
10 months after consent

Screening a site of your own?

RedlineUK · £39

West Suffolk approves 97% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Rookwood Way - Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Suffolk’s record on solar

West Suffolk has decided 29 solar farms and approved 97%, taking a median of 2.9 months. See every solar farm decision in West Suffolk

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
31.68.3 km
Solar Photovoltaics · Under Construction
49.9911.6 km
Battery · Operational
2011.7 km
Solar Photovoltaics · Operational
4.912.7 km
Solar Photovoltaics · Operational
1912.9 km
Solar Photovoltaics · Operational
1213 km
Wind Onshore · Operational
2613.1 km
Solar Photovoltaics · Operational
10.813.5 km

How big is Rookwood Way - Solar Farm?

Rookwood Way - Solar Farm has a recorded installed capacity of 2.04 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Rookwood Way - Solar Farm?

REPD records the operator as Sanofi UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Rookwood Way - Solar Farm approved and built?

The application was submitted on 3 February 2023. Permission was granted on 29 June 2023, 5 months later. The site became operational on 1 May 2024, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12682.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode