Renewable sites › Claredown Farm
Claredown Farm
Claredown Farm is operational in Braintree with a recorded capacity of 20 MW, and has been generating since 2018-02-27.
Planning and build timeline
| Application submitted | 2017-04-04 |
| Permission granted | 2017-08-02 4 months after submission |
| Operational | 2018-02-27 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Braintree’s record on battery storage
Braintree has decided 8 battery storage schemes and approved 100%, taking a median of 3.9 months. See every battery storage scheme decision in Braintree →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Cutbush Farm, Belchamp St Paul - Solar Array Solar Photovoltaics · Under Construction | 49.99 | 2.1 km |
Pentlow Hill Solar Photovoltaics · Operational | 24 | 3.9 km |
Broxted Solar Farm (Stradishall Airfield) Solar Photovoltaics · Operational | 31.6 | 9.2 km |
Rookwood Way - Solar Farm Solar Photovoltaics · Operational | 2.04 | 11.7 km |
Gosfield Airfield Solar Photovoltaics · Operational | 12.6 | 12.9 km |
Halstead Renewable Power Project (Waste AD) Anaerobic Digestion · Operational | 2 | 14.7 km |
How big is Claredown Farm?
Claredown Farm has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Claredown Farm?
REPD records the operator as Zenobe (formerly Energy Reservoir 15). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Claredown Farm approved and built?
The application was submitted on 2017-04-04. Permission was granted on 2017-08-02, 4 months later. The site became operational on 2018-02-27, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6945.