Renewable sites › Wadlow Wind Farm
Wadlow Wind Farm
Wadlow Wind Farm is operational in South Cambridgeshire with a recorded capacity of 26 MW, and has been generating since 2012-09-01.
Planning and build timeline
| Application submitted | 2006-05-15 |
| Permission granted | 2009-11-09 42 months after submission |
| Operational | 2012-09-01 34 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Great Wilbraham Solar Farm Solar Photovoltaics · Operational | 38.1 | 3.8 km |
Exning Solar Photovoltaics · Operational | 29.9 | 9.6 km |
Burwell - Battery Storage Battery · Operational | 50 | 12.5 km |
Rookwood Way - Solar Farm Solar Photovoltaics · Operational | 2.04 | 13.1 km |
Burwell Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 13.2 km |
Forest Heath Solar Farm Solar Photovoltaics · Operational | 5 | 13.6 km |
Milton Landfill Site Landfill Gas · Operational | 2 | 13.7 km |
Goosehall Solar Farm Solar Photovoltaics · Operational | 39.5 | 14.2 km |
How big is Wadlow Wind Farm?
Wadlow Wind Farm has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wadlow Wind Farm?
REPD records the operator as DIF. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wadlow Wind Farm approved and built?
The application was submitted on 2006-05-15. Permission was granted on 2009-11-09, 42 months later. The site became operational on 2012-09-01, 34 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3935.