Cutbush Farm, Belchamp St Paul - Solar Array
Cutbush Farm, Belchamp St Paul - Solar Array is under construction in Braintree with a recorded capacity of 49.99 MW.
Planning and build timeline
| Application submitted | 2023-05-31 |
| Permission granted | 2024-12-09 18 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Braintree’s record on solar
Braintree has decided 23 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Braintree →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Claredown Farm Battery · Operational | 20 | 2.1 km |
Pentlow Hill Solar Photovoltaics · Operational | 24 | 5 km |
Broxted Solar Farm (Stradishall Airfield) Solar Photovoltaics · Operational | 31.6 | 10.6 km |
Gosfield Airfield Solar Photovoltaics · Operational | 12.6 | 10.9 km |
Rookwood Way - Solar Farm Solar Photovoltaics · Operational | 2.04 | 11.6 km |
Halstead Renewable Power Project (Waste AD) Anaerobic Digestion · Operational | 2 | 12.9 km |
How big is Cutbush Farm, Belchamp St Paul - Solar Array?
Cutbush Farm, Belchamp St Paul - Solar Array has a recorded installed capacity of 49.99 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cutbush Farm, Belchamp St Paul - Solar Array?
REPD records the operator as British Solar Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cutbush Farm, Belchamp St Paul - Solar Array approved and built?
The application was submitted on 2023-05-31. Permission was granted on 2024-12-09, 18 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11329.