Novarly ParcelRenewable sites

Renewable sitesRiverside Resource Recovery Facility (RRRF)

Riverside Resource Recovery Facility (RRRF)

Riverside Resource Recovery Facility (RRRF) is operational in Bexley with a recorded capacity of 72 MW, and has been generating since 2011-09-01.

72 MW
Capacity
as recorded in REPD
Operational
Status
since 2011-09-01
EfW Incineration
Technology
Cory Environmental
Bexley
Authority
England

Planning and build timeline

Application submitted1999-09-29
Permission granted2006-06-15
81 months after submission
Operational2011-09-01
63 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Crossness Sewage Works Turbine
Wind Onshore · Operational
2.54.1 km
Crossness Sewage Works
Sewage Sludge Digestion · Operational
5.74.1 km
Twin Tumps Way - Solar Panels
Solar Photovoltaics · Operational
0.624.3 km
Crossness Sewage Works PV
Solar Photovoltaics · Operational
1.54.6 km
Riverside Resource Recovery Facility Battery Storage
Battery · Under Construction
2.54.8 km
Beckton STW Biodiesel Power Plant
Biomass (dedicated) · Operational
85.8 km
Rainham Phase II
Landfill Gas · Operational
175.8 km
Rainham Landfill Scheme, Phase I
Landfill Gas · Operational
3.95.8 km

How big is Riverside Resource Recovery Facility (RRRF)?

Riverside Resource Recovery Facility (RRRF) has a recorded installed capacity of 72 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Riverside Resource Recovery Facility (RRRF)?

REPD records the operator as Cory Environmental. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Riverside Resource Recovery Facility (RRRF) approved and built?

The application was submitted on 1999-09-29. Permission was granted on 2006-06-15, 81 months later. The site became operational on 2011-09-01, 63 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 859.