Renewable sites › Rainham Landfill Scheme, Phase I
Rainham Landfill Scheme, Phase I
Rainham Landfill Scheme, Phase I is operational in Havering with a recorded capacity of 3.9 MW, and has been generating since 2000-02-28.
Planning and build timeline
| Application submitted | 1996-11-08 |
| Permission granted | 1998-02-06 15 months after submission |
| Operational | 2000-02-28 25 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rainham Phase II Landfill Gas · Operational | 17 | 0 km |
Riverside Sewage Treatment Works Digestion Plant Sewage Sludge Digestion · Operational | 4 | 3 km |
Aveley Landfill Gas · Operational | 1.2 | 3.1 km |
Riverside Resource Recovery Facility Battery Storage Battery · Under Construction | 2.5 | 3.1 km |
Aveley Landfill Scheme Landfill Gas · Operational | 2.1 | 3.2 km |
Sandy Lane Landfill Scheme Landfill Gas · Operational | 2.3 | 3.8 km |
Longreach STW - extension Sewage Sludge Digestion · Operational | 1.1 | 3.8 km |
Crossness Sewage Works Turbine Wind Onshore · Operational | 2.5 | 3.8 km |
How big is Rainham Landfill Scheme, Phase I?
Rainham Landfill Scheme, Phase I has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rainham Landfill Scheme, Phase I?
REPD records the operator as Cleanaway / EDL. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rainham Landfill Scheme, Phase I approved and built?
The application was submitted on 1996-11-08. Permission was granted on 1998-02-06, 15 months later. The site became operational on 2000-02-28, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 725.