Renewable sites › Riverside Resource Recovery Facility Battery Storage
Riverside Resource Recovery Facility Battery Storage
Riverside Resource Recovery Facility Battery Storage is a 2.5 MW battery storage site under construction in Bexley. REPD does not record the planning grant date. Operator of record: Riverside Resource Recovery Limited.
Planning and build timeline
| Application submitted | 9 December 2020 |
| Permission granted | not recorded |
| Operational | not recorded |
Screening a site of your own?
Redline runs the record on your own boundary in Bexley: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Riverside Resource Recovery Facility Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 2.5 | 1 km |
Sewage Sludge Digestion · Operational | 5.7 | 1 km |
Solar Photovoltaics · Operational | 1.5 | 1.3 km |
Wind Onshore · Operational | 5.9 | 1.6 km |
Anaerobic Digestion · Operational | 1.4 | 2.2 km |
Sewage Sludge Digestion · Operational | 4 | 2.5 km |
Anaerobic Digestion · Operational | 1.4 | 2.5 km |
Wind Onshore · Operational | 2 | 2.7 km |
How big is Riverside Resource Recovery Facility Battery Storage?
Riverside Resource Recovery Facility Battery Storage has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Riverside Resource Recovery Facility Battery Storage?
REPD records the operator as Riverside Resource Recovery Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Riverside Resource Recovery Facility Battery Storage approved and built?
The application was submitted on 9 December 2020. REPD does not record a grant date. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8261.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode