Renewable sites › Rhodders Wind Farm
Rhodders Wind Farm
Rhodders Wind Farm is operational in Clackmannanshire with a recorded capacity of 12 MW, and has been generating since 2016-02-29.
Planning and build timeline
| Application submitted | 2011-11-07 |
| Permission granted | 2014-01-21 26 months after submission |
| Operational | 2016-02-29 25 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Burnfoot Hill Wind Onshore · Operational | 26 | 0.8 km |
Burnfoot East Wind Farm (further extension) Wind Onshore · Operational | 10.8 | 1.5 km |
Burnfoot Hill Extension Wind Onshore · Operational | 4 | 1.5 km |
Balhearty Solar Solar Photovoltaics · Operational | 5 | 8.1 km |
Devilla Energy Storage Facility Battery · Under Construction | 500 | 8.1 km |
Green Knowes Wind Onshore · Operational | 27 | 8.8 km |
Gleneagles Hotel Biomass Boiler Plant Room Biomass (dedicated) · Operational | 1.2 | 9 km |
Strathallan Wind Farm Wind Onshore · Under Construction | 20.7 | 13.5 km |
How big is Rhodders Wind Farm?
Rhodders Wind Farm has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rhodders Wind Farm?
REPD records the operator as EDF/Wind Prospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rhodders Wind Farm approved and built?
The application was submitted on 2011-11-07. Permission was granted on 2014-01-21, 26 months later. The site became operational on 2016-02-29, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4223.