Renewable sites › Rhodders Wind Farm
Rhodders Wind Farm
Rhodders Wind Farm is an operational 12 MW onshore wind farm in Clackmannanshire, generating since 29 February 2016. Planning permission was granted on 21 January 2014, 26 months after submission. Operator of record: EDF/Wind Prospect.
Planning and build timeline
| Application submitted | 7 November 2011 |
| Permission granted | 21 January 2014 26 months after submission |
| Operational | 29 February 2016 25 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Clackmannanshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Rhodders Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 26 | 0.8 km |
Wind Onshore · Operational | 10.8 | 1.5 km |
Wind Onshore · Operational | 4 | 1.5 km |
Solar Photovoltaics · Operational | 5 | 8.1 km |
Battery · Under Construction | 500 | 8.1 km |
Wind Onshore · Operational | 27 | 8.8 km |
Biomass (dedicated) · Operational | 1.2 | 9 km |
Wind Onshore · Under Construction | 20.7 | 13.5 km |
How big is Rhodders Wind Farm?
Rhodders Wind Farm has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rhodders Wind Farm?
REPD records the operator as EDF/Wind Prospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rhodders Wind Farm approved and built?
The application was submitted on 7 November 2011. Permission was granted on 21 January 2014, 26 months later. The site became operational on 29 February 2016, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4223.