Renewable sitesBurnfoot Hill

Burnfoot Hill

Burnfoot Hill is an operational 26 MW onshore wind farm in Clackmannanshire, generating since 26 October 2010. Planning permission was granted on 28 March 2007, 12 months after submission. Operator of record: EDF Energies Nouvelles.

26 MW
Capacity
as recorded in REPD
Operational
Status
since 26 October 2010
Wind Onshore
Technology
EDF Energies Nouvelles
Clackmannanshire
Authority
Scotland

Planning and build timeline

Application submitted20 March 2006
Permission granted28 March 2007
12 months after submission
Operational26 October 2010
43 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Clackmannanshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Burnfoot Hill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
40.7 km
Wind Onshore · Operational
10.80.8 km
Wind Onshore · Operational
120.8 km
Wind Onshore · Operational
278 km
Solar Photovoltaics · Operational
58.3 km
Biomass (dedicated) · Operational
1.28.4 km
Battery · Under Construction
5008.7 km
Wind Onshore · Under Construction
20.713.5 km

How big is Burnfoot Hill?

Burnfoot Hill has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Burnfoot Hill?

REPD records the operator as EDF Energies Nouvelles. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Burnfoot Hill approved and built?

The application was submitted on 20 March 2006. Permission was granted on 28 March 2007, 12 months later. The site became operational on 26 October 2010, 43 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2902.