Renewable sites › Burnfoot East Wind Farm (further extension)
Burnfoot East Wind Farm (further extension)
Burnfoot East Wind Farm (further extension) is an operational 10.8 MW onshore wind farm in Clackmannanshire, generating since 1 July 2020. Planning permission was granted on 27 March 2019, 26 months after submission. Operator of record: Wind Prospect Developments.
Planning and build timeline
| Application submitted | 30 January 2017 |
| Permission granted | 27 March 2019 26 months after submission |
| Operational | 1 July 2020 15 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Clackmannanshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Burnfoot East Wind Farm (further extension)’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 26 | 0.8 km |
Wind Onshore · Operational | 4 | 0.9 km |
Wind Onshore · Operational | 12 | 1.5 km |
Wind Onshore · Operational | 27 | 7.3 km |
Solar Photovoltaics · Operational | 5 | 7.9 km |
Biomass (dedicated) · Operational | 1.2 | 8.3 km |
Battery · Under Construction | 500 | 8.8 km |
Wind Onshore · Under Construction | 20.7 | 14 km |
How big is Burnfoot East Wind Farm (further extension)?
Burnfoot East Wind Farm (further extension) has a recorded installed capacity of 10.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Burnfoot East Wind Farm (further extension)?
REPD records the operator as Wind Prospect Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Burnfoot East Wind Farm (further extension) approved and built?
The application was submitted on 30 January 2017. Permission was granted on 27 March 2019, 26 months later. The site became operational on 1 July 2020, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6324.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode