Renewable sites › Burnfoot East Wind Farm (further extension)
Burnfoot East Wind Farm (further extension)
Burnfoot East Wind Farm (further extension) is operational in Clackmannanshire with a recorded capacity of 10.8 MW, and has been generating since 2020-07-01.
Planning and build timeline
| Application submitted | 2017-01-30 |
| Permission granted | 2019-03-27 26 months after submission |
| Operational | 2020-07-01 15 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Burnfoot Hill Wind Onshore · Operational | 26 | 0.8 km |
Burnfoot Hill Extension Wind Onshore · Operational | 4 | 0.9 km |
Rhodders Wind Farm Wind Onshore · Operational | 12 | 1.5 km |
Green Knowes Wind Onshore · Operational | 27 | 7.3 km |
Balhearty Solar Solar Photovoltaics · Operational | 5 | 7.9 km |
Gleneagles Hotel Biomass Boiler Plant Room Biomass (dedicated) · Operational | 1.2 | 8.3 km |
Devilla Energy Storage Facility Battery · Under Construction | 500 | 8.8 km |
Strathallan Wind Farm Wind Onshore · Under Construction | 20.7 | 14 km |
How big is Burnfoot East Wind Farm (further extension)?
Burnfoot East Wind Farm (further extension) has a recorded installed capacity of 10.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Burnfoot East Wind Farm (further extension)?
REPD records the operator as Wind Prospect Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Burnfoot East Wind Farm (further extension) approved and built?
The application was submitted on 2017-01-30. Permission was granted on 2019-03-27, 26 months later. The site became operational on 2020-07-01, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6324.
Novarly Parcel · official public data, read properly · parcel.novarly.com