Novarly ParcelRenewable sites

Renewable sitesStrathallan Wind Farm

Strathallan Wind Farm

Strathallan Wind Farm is under construction in Perth and Kinross with a recorded capacity of 20.7 MW.

20.7 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Green Cat Renewables
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted2015-10-12
Permission granted2019-01-15
39 months after submission
Operationalnot recorded

Perth and Kinross’s record on onshore wind

Perth and Kinross has decided 27 onshore wind schemes and approved 48%, taking a median of 15.2 months. See every onshore wind scheme decision in Perth and Kinross

Other built sites within 15 km

SiteMWDistance
Braes O'Doune
Wind Onshore · Operational
728.9 km
Lednock
Small Hydro · Operational
39.8 km
Turret water treatment works
Small Hydro · Operational
1.910 km
Gleneagles Hotel Biomass Boiler Plant Room
Biomass (dedicated) · Operational
1.210.7 km
Dalchonzie
Small Hydro · Operational
411.2 km
Burnfoot Hill Extension
Wind Onshore · Operational
413.2 km
Burnfoot Hill
Wind Onshore · Operational
2613.5 km
Rhodders Wind Farm
Wind Onshore · Operational
1213.5 km

How big is Strathallan Wind Farm?

Strathallan Wind Farm has a recorded installed capacity of 20.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Strathallan Wind Farm?

REPD records the operator as Green Cat Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Strathallan Wind Farm approved and built?

The application was submitted on 2015-10-12. Permission was granted on 2019-01-15, 39 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2860.