Renewable sites › Balhearty Solar
Balhearty Solar
Balhearty Solar is operational in Clackmannanshire with a recorded capacity of 5 MW, and has been generating since 2016-03-31.
Planning and build timeline
| Application submitted | 2015-10-20 |
| Permission granted | 2015-12-23 2 months after submission |
| Operational | 2016-03-31 3 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Devilla Energy Storage Facility Battery · Under Construction | 500 | 4.6 km |
Burnfoot East Wind Farm (further extension) Wind Onshore · Operational | 10.8 | 7.9 km |
Rhodders Wind Farm Wind Onshore · Operational | 12 | 8.1 km |
Burnfoot Hill Wind Onshore · Operational | 26 | 8.3 km |
Burnfoot Hill Extension Wind Onshore · Operational | 4 | 8.8 km |
Cowie Biomass Facility Biomass (dedicated) · Operational | 15 | 12 km |
Green Knowes Wind Onshore · Operational | 27 | 12.2 km |
Rosehill Wind Turbines Wind Onshore · Operational | 2.4 | 12.2 km |
How big is Balhearty Solar?
Balhearty Solar has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Balhearty Solar?
REPD records the operator as NESF (formerly Lark Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Balhearty Solar approved and built?
The application was submitted on 2015-10-20. Permission was granted on 2015-12-23, 2 months later. The site became operational on 2016-03-31, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5795.
Novarly Parcel · official public data, read properly · parcel.novarly.com