Renewable sitesBalhearty Solar

Balhearty Solar

Balhearty Solar is operational in Clackmannanshire with a recorded capacity of 5 MW, and has been generating since 2016-03-31.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-31
Solar Photovoltaics
Technology
NESF (formerly Lark Energy)
Clackmannanshire
Authority
Scotland

Planning and build timeline

Application submitted2015-10-20
Permission granted2015-12-23
2 months after submission
Operational2016-03-31
3 months after consent

Other built sites within 15 km

SiteMWDistance
Devilla Energy Storage Facility
Battery · Under Construction
5004.6 km
Burnfoot East Wind Farm (further extension)
Wind Onshore · Operational
10.87.9 km
Rhodders Wind Farm
Wind Onshore · Operational
128.1 km
Burnfoot Hill
Wind Onshore · Operational
268.3 km
Burnfoot Hill Extension
Wind Onshore · Operational
48.8 km
Cowie Biomass Facility
Biomass (dedicated) · Operational
1512 km
Green Knowes
Wind Onshore · Operational
2712.2 km
Rosehill Wind Turbines
Wind Onshore · Operational
2.412.2 km

How big is Balhearty Solar?

Balhearty Solar has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Balhearty Solar?

REPD records the operator as NESF (formerly Lark Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Balhearty Solar approved and built?

The application was submitted on 2015-10-20. Permission was granted on 2015-12-23, 2 months later. The site became operational on 2016-03-31, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5795.