Renewable sitesBurnfoot Hill Extension

Burnfoot Hill Extension

Burnfoot Hill Extension is operational in Perth and Kinross with a recorded capacity of 4 MW, and has been generating since 2014-09-09.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-09-09
Wind Onshore
Technology
Private Developer
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted2011-12-09
Permission granted2013-04-02
16 months after submission
Operational2014-09-09
17 months after consent

Perth and Kinross’s record on onshore wind

Perth and Kinross has decided 27 onshore wind schemes and approved 48%, taking a median of 15.2 months. See every onshore wind scheme decision in Perth and Kinross

Other built sites within 15 km

SiteMWDistance
Burnfoot Hill
Wind Onshore · Operational
260.7 km
Burnfoot East Wind Farm (further extension)
Wind Onshore · Operational
10.80.9 km
Rhodders Wind Farm
Wind Onshore · Operational
121.5 km
Green Knowes
Wind Onshore · Operational
277.4 km
Gleneagles Hotel Biomass Boiler Plant Room
Biomass (dedicated) · Operational
1.27.6 km
Balhearty Solar
Solar Photovoltaics · Operational
58.8 km
Devilla Energy Storage Facility
Battery · Under Construction
5009.4 km
Strathallan Wind Farm
Wind Onshore · Under Construction
20.713.2 km

How big is Burnfoot Hill Extension?

Burnfoot Hill Extension has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Burnfoot Hill Extension?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Burnfoot Hill Extension approved and built?

The application was submitted on 2011-12-09. Permission was granted on 2013-04-02, 16 months later. The site became operational on 2014-09-09, 17 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4450.