Renewable sites › Green Knowes
Green Knowes
Green Knowes is an operational 27 MW onshore wind farm in Perth and Kinross, generating since 29 September 2008. Planning permission was granted on 13 June 2008, 46 months after submission. Operator of record: CRE Energy/ Scottish Power.
Planning and build timeline
| Application submitted | 4 August 2004 |
| Permission granted | 13 June 2008 46 months after submission |
| Operational | 29 September 2008 4 months after consent |
Screening a site of your own?
Perth and Kinross approves 48% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Green Knowes’s recorded coordinate — swap in your own postcode or coordinates.
Perth and Kinross’s record on onshore wind
Perth and Kinross has decided 27 onshore wind schemes and approved 48%, taking a median of 15.2 months. See every onshore wind scheme decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Biomass (dedicated) · Operational | 1.2 | 6.5 km |
Wind Onshore · Operational | 10.8 | 7.3 km |
Wind Onshore · Operational | 4 | 7.4 km |
Wind Onshore · Operational | 26 | 8 km |
Wind Onshore · Operational | 12 | 8.8 km |
Solar Photovoltaics · Operational | 5 | 12.2 km |
Battery · Under Construction | 500 | 15 km |
How big is Green Knowes?
Green Knowes has a recorded installed capacity of 27 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Green Knowes?
REPD records the operator as CRE Energy/ Scottish Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Green Knowes approved and built?
The application was submitted on 4 August 2004. Permission was granted on 13 June 2008, 46 months later. The site became operational on 29 September 2008, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3487.