Planning and build timeline
| Application submitted | 19 November 2020 |
| Permission granted | 4 February 2021 3 months after submission |
| Operational | 1 October 2021 8 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Gleneagles Hotel Biomass Boiler Plant Room’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 27 | 6.5 km |
Wind Onshore · Operational | 4 | 7.6 km |
Wind Onshore · Operational | 10.8 | 8.3 km |
Wind Onshore · Operational | 26 | 8.4 km |
Wind Onshore · Operational | 12 | 9 km |
Wind Onshore · Under Construction | 20.7 | 10.7 km |
Small Hydro · Operational | 1.9 | 11.3 km |
How big is Gleneagles Hotel Biomass Boiler Plant Room?
Gleneagles Hotel Biomass Boiler Plant Room has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gleneagles Hotel Biomass Boiler Plant Room?
REPD records the operator as AMP Energy Services Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gleneagles Hotel Biomass Boiler Plant Room approved and built?
The application was submitted on 19 November 2020. Permission was granted on 4 February 2021, 3 months later. The site became operational on 1 October 2021, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8188.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode