Gleneagles Hotel Biomass Boiler Plant Room is operational in Perth and Kinross with a recorded capacity of 1.2 MW, and has been generating since 2021-10-01.

1.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-10-01
Biomass (dedicated)
Technology
AMP Energy Services Limited
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted2020-11-19
Permission granted2021-02-04
3 months after submission
Operational2021-10-01
8 months after consent

Other built sites within 15 km

SiteMWDistance
Green Knowes
Wind Onshore · Operational
276.5 km
Burnfoot Hill Extension
Wind Onshore · Operational
47.6 km
Burnfoot East Wind Farm (further extension)
Wind Onshore · Operational
10.88.3 km
Burnfoot Hill
Wind Onshore · Operational
268.4 km
Rhodders Wind Farm
Wind Onshore · Operational
129 km
Strathallan Wind Farm
Wind Onshore · Under Construction
20.710.7 km
Turret water treatment works
Small Hydro · Operational
1.911.3 km

How big is Gleneagles Hotel Biomass Boiler Plant Room?

Gleneagles Hotel Biomass Boiler Plant Room has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gleneagles Hotel Biomass Boiler Plant Room?

REPD records the operator as AMP Energy Services Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gleneagles Hotel Biomass Boiler Plant Room approved and built?

The application was submitted on 2020-11-19. Permission was granted on 2021-02-04, 3 months later. The site became operational on 2021-10-01, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8188.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council