Red Tile

Red Tile is an operational 24 MW onshore wind farm in Huntingdonshire, generating since 1 December 2006. Planning permission was granted on 7 February 2005, 16 months after submission. Operator of record: Wind Prospect Developments.

24 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2006
Wind Onshore
Technology
Wind Prospect Developments
Huntingdonshire
Authority
England

Planning and build timeline

Application submitted15 October 2003
Permission granted7 February 2005
16 months after submission
Operational1 December 2006
22 months after consent

Screening a site of your own?

RedlineUK · £39

Huntingdonshire approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Red Tile’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Huntingdonshire’s record on onshore wind

Huntingdonshire has decided 10 onshore wind schemes and approved 80%, taking a median of 13.9 months. See every onshore wind scheme decision in Huntingdonshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.25.1 km
Solar Photovoltaics · Operational
4.65.5 km
Wind Onshore · Operational
1.85.5 km
Solar Photovoltaics · Operational
57.2 km
Wind Onshore · Operational
87.6 km
Solar Photovoltaics · Operational
57.7 km
Anaerobic Digestion · Operational
14.48 km
Solar Photovoltaics · Operational
4.18.9 km

How big is Red Tile?

Red Tile has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Red Tile?

REPD records the operator as Wind Prospect Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Red Tile approved and built?

The application was submitted on 15 October 2003. Permission was granted on 7 February 2005, 16 months later. The site became operational on 1 December 2006, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3608.