Ramsey Wind Farm Extension is operational in Huntingdonshire with a recorded capacity of 8 MW, and has been generating since 2015-04-23.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-04-23
Wind Onshore
Technology
REG Windpower
Huntingdonshire
Authority
England

Planning and build timeline

Application submitted2011-11-08
Permission granted2013-05-22
18 months after submission
Operational2015-04-23
23 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Huntingdonshire’s record on onshore wind

Huntingdonshire has decided 10 onshore wind schemes and approved 80%, taking a median of 13.9 months. See every onshore wind scheme decision in Huntingdonshire

Other built sites within 15 km

SiteMWDistance
Bury Green Farm Solar
Solar Photovoltaics · Operational
52.1 km
Ramsey 1
Wind Onshore · Operational
1.82.6 km
Land at Biggin Lane
Solar Photovoltaics · Operational
52.7 km
Glass Moor
Wind Onshore · Operational
165.7 km
Glass moor Extension
Wind Onshore · Operational
125.7 km
Red Tile
Wind Onshore · Operational
247.6 km
Black Bush Farm
Solar Photovoltaics · Operational
2.79.2 km
Turves/Burtnhouse Solar Farm Extension
Solar Photovoltaics · Operational
4.79.4 km

How big is Ramsey Wind Farm Extension?

Ramsey Wind Farm Extension has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ramsey Wind Farm Extension?

REPD records the operator as REG Windpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ramsey Wind Farm Extension approved and built?

The application was submitted on 2011-11-08. Permission was granted on 2013-05-22, 18 months later. The site became operational on 2015-04-23, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4414.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council