Renewable sites › Ramsey 1
Ramsey 1
Ramsey 1 is operational in Huntingdonshire with a recorded capacity of 1.8 MW, and has been generating since 2008-09-30.
Planning and build timeline
| Application submitted | 2003-03-11 |
| Permission granted | 2004-04-23 13 months after submission |
| Operational | 2008-09-30 53 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Conservation area — RAMSEY AND BURY
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Huntingdonshire’s record on onshore wind
Huntingdonshire has decided 10 onshore wind schemes and approved 80%, taking a median of 13.9 months. See every onshore wind scheme decision in Huntingdonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land at Biggin Lane Solar Photovoltaics · Operational | 5 | 1.8 km |
Bury Green Farm Solar Solar Photovoltaics · Operational | 5 | 2.1 km |
Ramsey Wind Farm Extension Wind Onshore · Operational | 8 | 2.6 km |
Red Tile Wind Onshore · Operational | 24 | 5.5 km |
Glass Moor Wind Onshore · Operational | 16 | 8 km |
Glass moor Extension Wind Onshore · Operational | 12 | 8 km |
Lodge Farm Solar Photovoltaics · Operational | 2.4 | 8.7 km |
Abbey Farm Solar Photovoltaics · Operational | 9 | 9.4 km |
How big is Ramsey 1?
Ramsey 1 has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ramsey 1?
REPD records the operator as REG Windpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ramsey 1 approved and built?
The application was submitted on 2003-03-11. Permission was granted on 2004-04-23, 13 months later. The site became operational on 2008-09-30, 53 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3155.