Novarly ParcelRenewable planning

Renewable planning Onshore windHuntingdonshire

Onshore wind planning in Huntingdonshire

Huntingdonshire has decided 10 onshore wind schemes and approved 80% of them, taking a median of 13.9 months to decide. Consented capacity: 71 MW. 1 application still awaiting a decision.

80%
Approved
8 granted · 2 refused
13.9 mo
Median decision
UK 11.5 mo
71 MW
Consented
24 MW refused
5
Appeals
3 allowed on appeal

How Huntingdonshire compares

Against the 75 UK authorities with 5+ onshore wind decisions, Huntingdonshire sits in the 72nd percentile for approval rate (12 points above the England average) and the 53rd percentile for speed.

Decisions by year

35Approved — 1 (2010)110Approved — 1 (2012)112Approved — 2 (2013)Refused — 1 (2013)313Refused — 1 (2014)114Approved — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (11)

SchemeMWStatusDecided
Tick Fen Farm, Puddock Road - Wind Turbine
Whittome Renewables Limited · 25/00844/FUL · 1.8 mo to decide
0.5Awaiting Construction2025-07-16
Tick Fen Farm, Puddock Road - Wind Turbine
Whittome Farms · 24/00311/FUL · 2.2 mo to decide
0.5Awaiting Construction2024-05-17
RAF Molesworth Wind Farm
RWE Npower Renewables · 1200967FUL · 22.4 mo to decide
15Application Refused2014-05-02
Bicton Wind Farm
Broadview Energy · 1300512FUL · 5.2 mo to decide
9Application Refused2013-09-18
Common Barn Wind Farm
TCI Renewables · 1200803FUL · 13.9 mo to decide
6.2Operational2013-07-11
Ramsey Wind Farm Extension
REG Windpower · 1101865FUL · 18.4 mo to decide
8Operational2013-05-22
Woolley Hill Wind Farm
Aviva · 1001741FUL · 16.4 mo to decide
10Operational2012-03-23
Bicton Wind Farm
Broadview Energy · 1001201FUL · 6.4 mo to decide
23Revised2011-01-20
Cotton Farm
Greencoat UK Wind · 0802296FUL · 28.3 mo to decide
20Operational2010-12-14
Red Tile
Wind Prospect Developments · 0302827FUL · 15.8 mo to decide
24Operational2005-02-07
Ramsey 1
REG Windpower · 0300478/FUL · 13.4 mo to decide
1.8Operational2004-04-23

Does Huntingdonshire approve onshore wind schemes?

Yes — of the 10 onshore wind schemes Huntingdonshire has decided, 80% were approved (8 granted, 2 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Huntingdonshire?

The median time from application to decision is 13.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Huntingdonshire consented?

71 MW has been consented across 8 approved schemes, with 24 MW refused. A further 1 application awaits a decision.

Other technologies in Huntingdonshire

Solar in HuntingdonshireBattery storage in Huntingdonshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report