Renewable planning › Onshore wind › Huntingdonshire
Onshore wind planning in Huntingdonshire
Huntingdonshire has decided 10 onshore wind schemes and approved 80% of them, taking a median of 13.9 months to decide. Consented capacity: 71 MW. 1 application still awaiting a decision.
How Huntingdonshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, Huntingdonshire sits in the 72nd percentile for approval rate (12 points above the England average) and the 53rd percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (11)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Tick Fen Farm, Puddock Road - Wind Turbine Whittome Renewables Limited · 25/00844/FUL · 1.8 mo to decide | 0.5 | Awaiting Construction | 2025-07-16 |
Tick Fen Farm, Puddock Road - Wind Turbine Whittome Farms · 24/00311/FUL · 2.2 mo to decide | 0.5 | Awaiting Construction | 2024-05-17 |
RAF Molesworth Wind Farm RWE Npower Renewables · 1200967FUL · 22.4 mo to decide | 15 | Application Refused | 2014-05-02 |
Bicton Wind Farm Broadview Energy · 1300512FUL · 5.2 mo to decide | 9 | Application Refused | 2013-09-18 |
Common Barn Wind Farm TCI Renewables · 1200803FUL · 13.9 mo to decide | 6.2 | Operational | 2013-07-11 |
Ramsey Wind Farm Extension REG Windpower · 1101865FUL · 18.4 mo to decide | 8 | Operational | 2013-05-22 |
Woolley Hill Wind Farm Aviva · 1001741FUL · 16.4 mo to decide | 10 | Operational | 2012-03-23 |
Bicton Wind Farm Broadview Energy · 1001201FUL · 6.4 mo to decide | 23 | Revised | 2011-01-20 |
Cotton Farm Greencoat UK Wind · 0802296FUL · 28.3 mo to decide | 20 | Operational | 2010-12-14 |
Red Tile Wind Prospect Developments · 0302827FUL · 15.8 mo to decide | 24 | Operational | 2005-02-07 |
Ramsey 1 REG Windpower · 0300478/FUL · 13.4 mo to decide | 1.8 | Operational | 2004-04-23 |
Does Huntingdonshire approve onshore wind schemes?
Yes — of the 10 onshore wind schemes Huntingdonshire has decided, 80% were approved (8 granted, 2 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in Huntingdonshire?
The median time from application to decision is 13.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Huntingdonshire consented?
71 MW has been consented across 8 approved schemes, with 24 MW refused. A further 1 application awaits a decision.
Other technologies in Huntingdonshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.