Novarly ParcelRenewable sites

Renewable sitesMepal CHP

Mepal CHP

Mepal CHP is operational in East Cambridgeshire with a recorded capacity of 14.4 MW, and has been generating since 2017-03-17.

14.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-17
Anaerobic Digestion
Technology
Pretoria Energy Company
East Cambridgeshire
Authority
England

Planning and build timeline

Application submitted2014-02-27
Permission granted2014-07-11
4 months after submission
Operational2017-03-17
32 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Alan Bartlett & Sons Solar
Solar Photovoltaics · Operational
1.24.2 km
Elean Business Park Biomass Plant
Biomass (dedicated) · Operational
404.4 km
Land East Of Honeysome Road
Solar Photovoltaics · Operational
4.64.6 km
Red Tile
Wind Onshore · Operational
248 km
Asksham Community Village Solar Farm
Solar Photovoltaics · Under Construction
0.158.6 km
Willow Farm
Solar Photovoltaics · Operational
1.159.8 km
Ranson Moor Wind Farm (Phase 2)
Wind Onshore · Operational
49.8 km
Ranson Moor (phase 1)
Wind Onshore · Operational
610.1 km

How big is Mepal CHP?

Mepal CHP has a recorded installed capacity of 14.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Mepal CHP?

REPD records the operator as Pretoria Energy Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mepal CHP approved and built?

The application was submitted on 2014-02-27. Permission was granted on 2014-07-11, 4 months later. The site became operational on 2017-03-17, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6578.