Renewable sites › Mepal CHP
Mepal CHP
Mepal CHP is operational in East Cambridgeshire with a recorded capacity of 14.4 MW, and has been generating since 2017-03-17.
Planning and build timeline
| Application submitted | 2014-02-27 |
| Permission granted | 2014-07-11 4 months after submission |
| Operational | 2017-03-17 32 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Alan Bartlett & Sons Solar Solar Photovoltaics · Operational | 1.2 | 4.2 km |
Elean Business Park Biomass Plant Biomass (dedicated) · Operational | 40 | 4.4 km |
Land East Of Honeysome Road Solar Photovoltaics · Operational | 4.6 | 4.6 km |
Red Tile Wind Onshore · Operational | 24 | 8 km |
Asksham Community Village Solar Farm Solar Photovoltaics · Under Construction | 0.15 | 8.6 km |
Willow Farm Solar Photovoltaics · Operational | 1.15 | 9.8 km |
Ranson Moor Wind Farm (Phase 2) Wind Onshore · Operational | 4 | 9.8 km |
Ranson Moor (phase 1) Wind Onshore · Operational | 6 | 10.1 km |
How big is Mepal CHP?
Mepal CHP has a recorded installed capacity of 14.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mepal CHP?
REPD records the operator as Pretoria Energy Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mepal CHP approved and built?
The application was submitted on 2014-02-27. Permission was granted on 2014-07-11, 4 months later. The site became operational on 2017-03-17, 32 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6578.