Renewable sites › Land at Biggin Lane
Land at Biggin Lane
Land at Biggin Lane is operational in Huntingdonshire with a recorded capacity of 5 MW, and has been generating since 2016-03-15.
Planning and build timeline
| Application submitted | 2015-05-13 |
| Permission granted | 2015-09-23 4 months after submission |
| Operational | 2016-03-15 6 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Huntingdonshire’s record on solar
Huntingdonshire has decided 33 solar farms and approved 97%, taking a median of 3.2 months. See every solar farm decision in Huntingdonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bury Green Farm Solar Solar Photovoltaics · Operational | 5 | 0.8 km |
Ramsey 1 Wind Onshore · Operational | 1.8 | 1.8 km |
Ramsey Wind Farm Extension Wind Onshore · Operational | 8 | 2.7 km |
Red Tile Wind Onshore · Operational | 24 | 7.2 km |
Abbey Farm Solar Photovoltaics · Operational | 9 | 7.6 km |
Lodge Farm Solar Photovoltaics · Operational | 2.4 | 8.3 km |
Glass Moor Wind Onshore · Operational | 16 | 8.3 km |
Glass moor Extension Wind Onshore · Operational | 12 | 8.3 km |
How big is Land at Biggin Lane?
Land at Biggin Lane has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Biggin Lane?
REPD records the operator as Ramsey Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Biggin Lane approved and built?
The application was submitted on 2015-05-13. Permission was granted on 2015-09-23, 4 months later. The site became operational on 2016-03-15, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5829.