Renewable sitesGlass moor Extension

Glass moor Extension

Glass moor Extension is operational in Fenland with a recorded capacity of 12 MW, and has been generating since 2013-03-31.

12 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-31
Wind Onshore
Technology
EDF/China General Nuclear Power Corporation
Fenland
Authority
England

Planning and build timeline

Application submitted2011-01-31
Permission granted2012-04-10
14 months after submission
Operational2013-03-31
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fenland’s record on onshore wind

Fenland has decided 20 onshore wind schemes and approved 85%, taking a median of 12.8 months. See every onshore wind scheme decision in Fenland

Other built sites within 15 km

SiteMWDistance
Glass Moor
Wind Onshore · Operational
160 km
Black Bush Farm
Solar Photovoltaics · Operational
2.74.4 km
Burnt House Farm
Wind Onshore · Operational
65.5 km
Ramsey Wind Farm Extension
Wind Onshore · Operational
85.7 km
Turves/Burtnhouse Solar Farm Extension
Solar Photovoltaics · Operational
4.75.7 km
Turves Solar Farm
Solar Photovoltaics · Operational
55.8 km
Whittlesey
Wind Onshore · Operational
96.1 km
McCain Foods AD Plant (AD)
Anaerobic Digestion · Operational
16.4 km

How big is Glass moor Extension?

Glass moor Extension has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Glass moor Extension?

REPD records the operator as EDF/China General Nuclear Power Corporation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Glass moor Extension approved and built?

The application was submitted on 2011-01-31. Permission was granted on 2012-04-10, 14 months later. The site became operational on 2013-03-31, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3765.