Novarly ParcelRenewable sites

Renewable sitesAveley

Aveley

Aveley is an operational 1.2 MW landfill gas site in Thurrock, generating since 20 July 1999. Planning permission was granted on 4 June 1998, 5 months after submission. Operator of record: Waste Recycling Group.

1.2 MW
Capacity
as recorded in REPD
Operational
Status
since 20 July 1999
Landfill Gas
Technology
Waste Recycling Group
Thurrock
Authority
England

Planning and build timeline

Application submitted13 January 1998
Permission granted4 June 1998
5 months after submission
Operational20 July 1999
14 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Thurrock: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Aveley’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
2.10.1 km
Landfill Gas · Operational
2.30.7 km
Landfill Gas · Operational
173.1 km
Landfill Gas · Operational
3.93.1 km
Sewage Sludge Digestion · Operational
43.6 km
Wind Onshore · Operational
13.7 km
Solar Photovoltaics · Operational
49.94.1 km
Sewage Sludge Digestion · Operational
1.14.2 km

How big is Aveley?

Aveley has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Aveley?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Aveley approved and built?

The application was submitted on 13 January 1998. Permission was granted on 4 June 1998, 5 months later. The site became operational on 20 July 1999, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 514.

Novarly Parcel · official public data, read properly · parcel.novarly.com