Renewable sites › Longreach STW - extension
Longreach STW - extension
Longreach STW - extension is an operational 1.1 MW sewage sludge digestion plant in Dartford, generating since 1 July 2014. Planning permission was granted on 15 October 2012, 1 months after submission. Operator of record: Thames Water Utilities.
Planning and build timeline
| Application submitted | 24 September 2012 |
| Permission granted | 15 October 2012 1 months after submission |
| Operational | 1 July 2014 20 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Dartford: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Longreach STW - extension’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | 7.5 | 1.4 km |
Landfill Gas · Operational | 17 | 3.8 km |
Landfill Gas · Operational | 3.9 | 3.8 km |
Landfill Gas · Operational | 2.1 | 4.2 km |
Landfill Gas · Operational | 1.2 | 4.2 km |
Landfill Gas · Operational | 2.3 | 4.2 km |
Solar Photovoltaics · Operational | 49.9 | 6.4 km |
Sewage Sludge Digestion · Operational | 4 | 6.4 km |
How big is Longreach STW - extension?
Longreach STW - extension has a recorded installed capacity of 1.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Longreach STW - extension?
REPD records the operator as Thames Water Utilities. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Longreach STW - extension approved and built?
The application was submitted on 24 September 2012. Permission was granted on 15 October 2012, 1 months later. The site became operational on 1 July 2014, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2392.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode