Novarly ParcelRenewable sites

Renewable sitesPoplars Anaerobic Digestion Facility (Waste AD)

Poplars Anaerobic Digestion Facility (Waste AD)

Poplars Anaerobic Digestion Facility (Waste AD) is an operational 6 MW anaerobic digestion plant in Cannock Chase, generating since 31 July 2011. Planning permission was granted on 15 January 2010, 6 months after submission. Operator of record: Biffa.

6 MW
Capacity
as recorded in REPD
Operational
Status
since 31 July 2011
Anaerobic Digestion
Technology
Biffa
Cannock Chase
Authority
England

Planning and build timeline

Application submitted13 July 2009
Permission granted15 January 2010
6 months after submission
Operational31 July 2011
18 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Cannock Chase: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Poplars Anaerobic Digestion Facility (Waste AD)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
EfW Incineration · Operational
237.4 km
Wind Onshore · Operational
47.5 km
Solar Photovoltaics · Operational
1.88.1 km
Landfill Gas · Operational
18.4 km
EfW Incineration · Under Construction
498.4 km
Solar Photovoltaics · Operational
510.2 km
Battery · Operational
4110.5 km
Solar Photovoltaics · Operational
5.810.5 km

How big is Poplars Anaerobic Digestion Facility (Waste AD)?

Poplars Anaerobic Digestion Facility (Waste AD) has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Poplars Anaerobic Digestion Facility (Waste AD)?

REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Poplars Anaerobic Digestion Facility (Waste AD) approved and built?

The application was submitted on 13 July 2009. Permission was granted on 15 January 2010, 6 months later. The site became operational on 31 July 2011, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 249.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode