Four Ashes EfW is an operational 23 MW energy-from-waste plant in South Staffordshire, generating since 14 May 2014. Planning permission was granted on 18 February 2011, 6 months after submission. Operator of record: Veolia.

23 MW
Capacity
as recorded in REPD
Operational
Status
since 14 May 2014
EfW Incineration
Technology
Veolia
South Staffordshire
Authority
England

Planning and build timeline

Application submitted19 August 2010
Permission granted18 February 2011
6 months after submission
Operational14 May 2014
39 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Staffordshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Four Ashes EfW’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.80.8 km
Wind Onshore · Operational
43.2 km
Solar Photovoltaics · Operational
54.1 km
Solar Photovoltaics · Operational
5.84.8 km
Anaerobic Digestion · Operational
67.4 km
EfW Incineration · Operational
88.6 km
Solar Photovoltaics · Under Construction
6.99.2 km
Battery · Operational
9.8 km

How big is Four Ashes EfW?

Four Ashes EfW has a recorded installed capacity of 23 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Four Ashes EfW?

REPD records the operator as Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Four Ashes EfW approved and built?

The application was submitted on 19 August 2010. Permission was granted on 18 February 2011, 6 months later. The site became operational on 14 May 2014, 39 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 911.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode