Rodbaston

Rodbaston is operational in South Staffordshire with a recorded capacity of 4 MW, and has been generating since 2017-01-15.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-01-15
Wind Onshore
Technology
REG Windpower
South Staffordshire
Authority
England

Planning and build timeline

Application submitted2009-07-16
Permission granted2010-12-15
17 months after submission
Operational2017-01-15
73 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Four Ashes EfW
EfW Incineration · Operational
233.2 km
Barr Farm
Solar Photovoltaics · Operational
1.83.8 km
Land East of Lawn Lane
Solar Photovoltaics · Operational
57.1 km
Poplars Anaerobic Digestion Facility (Waste AD)
Anaerobic Digestion · Operational
67.5 km
Jaguar Land Rover
Solar Photovoltaics · Operational
5.87.8 km
Brookfield Farm AD Plant (Farm AD)
Anaerobic Digestion · Operational
1.311.2 km
Albrighton Solar farm
Battery · Operational
11.4 km
Albrighton Solar farm
Solar Photovoltaics · Operational
15.811.4 km

How big is Rodbaston?

Rodbaston has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Rodbaston?

REPD records the operator as REG Windpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Rodbaston approved and built?

The application was submitted on 2009-07-16. Permission was granted on 2010-12-15, 17 months later. The site became operational on 2017-01-15, 73 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3673.