Plot 8 Protos/Ince Marshes is a 35 MW energy-from-waste plant under construction in Cheshire West and Chester. Planning permission was granted on 7 September 2017, 14 months after submission. Operator of record: This is Protos (Peel Environmental).

35 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
EfW Incineration
Technology
This is Protos (Peel Environmental)
Cheshire West and Chester
Authority
England

Planning and build timeline

Application submitted18 July 2016
Permission granted7 September 2017
14 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Cheshire West and Chester: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Plot 8 Protos/Ince Marshes’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Advanced Conversion Technologies · Operational
21.50.5 km
Wind Onshore · Operational
50.44.3 km
Solar Photovoltaics · Operational
0.224.6 km
Landfill Gas · Operational
65.1 km
Landfill Gas · Operational
1.65.1 km
EfW Incineration · Operational
1006.9 km
Advanced Conversion Technologies · Under Construction
287.9 km
Battery · Operational
578.2 km

How big is Plot 8 Protos/Ince Marshes?

Plot 8 Protos/Ince Marshes has a recorded installed capacity of 35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Plot 8 Protos/Ince Marshes?

REPD records the operator as This is Protos (Peel Environmental). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Plot 8 Protos/Ince Marshes approved and built?

The application was submitted on 18 July 2016. Permission was granted on 7 September 2017, 14 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6131.