Renewable sitesRuncorn EfW

Runcorn EfW

Runcorn EfW is operational in Halton with a recorded capacity of 100 MW, and has been generating since 2013-06-08.

100 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-06-08
EfW Incineration
Technology
INEOS Chlor / Viridor-Laing
Halton
Authority
England

Planning and build timeline

Application submitted2007-01-19
Permission granted2008-09-16
20 months after submission
Operational2013-06-08
57 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Leiria Way Car Park
Battery · Operational
2.3 km
Frodsham Marsh
Wind Onshore · Operational
50.43 km
Granox Biogas Plant
Anaerobic Digestion · Operational
53 km
Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant
Biomass (dedicated) · Operational
203.2 km
Ince Bio Power
Advanced Conversion Technologies · Operational
21.56.5 km
Fiddlers Ferry Power Station - Battery storage
Battery · Under Construction
1506.8 km
Plot 8 Protos/Ince Marshes
EfW Incineration · Under Construction
356.9 km
Daresbury Science Park - Solar Array
Solar Photovoltaics · Operational
0.567.8 km

How big is Runcorn EfW?

Runcorn EfW has a recorded installed capacity of 100 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Runcorn EfW?

REPD records the operator as INEOS Chlor / Viridor-Laing. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Runcorn EfW approved and built?

The application was submitted on 2007-01-19. Permission was granted on 2008-09-16, 20 months later. The site became operational on 2013-06-08, 57 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 932.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council