Runcorn EfW
Runcorn EfW is an operational 100 MW energy-from-waste plant in Halton, generating since 8 June 2013. Planning permission was granted on 16 September 2008, 20 months after submission. Operator of record: INEOS Chlor / Viridor-Laing.
Planning and build timeline
| Application submitted | 19 January 2007 |
| Permission granted | 16 September 2008 20 months after submission |
| Operational | 8 June 2013 57 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Halton: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Runcorn EfW’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | — | 2.3 km |
Wind Onshore · Operational | 50.4 | 3 km |
Anaerobic Digestion · Operational | 5 | 3 km |
Biomass (dedicated) · Operational | 20 | 3.2 km |
Advanced Conversion Technologies · Operational | 21.5 | 6.5 km |
Battery · Under Construction | 150 | 6.8 km |
EfW Incineration · Under Construction | 35 | 6.9 km |
Solar Photovoltaics · Operational | 0.56 | 7.8 km |
How big is Runcorn EfW?
Runcorn EfW has a recorded installed capacity of 100 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Runcorn EfW?
REPD records the operator as INEOS Chlor / Viridor-Laing. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Runcorn EfW approved and built?
The application was submitted on 19 January 2007. Permission was granted on 16 September 2008, 20 months later. The site became operational on 8 June 2013, 57 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 932.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode